Partial stop granted on ND pipeline work


Associated Press

WASHINGTON

An American Indian tribe succeeded Tuesday in getting a federal judge to temporarily stop construction on some, but not all, of a portion of a $3.8 billion four-state oil pipeline, but their broader request still hangs in the balance.

U.S. District Judge James Boasberg said Tuesday that work will temporarily stop between North Dakota’s State Highway 1806 and 20 miles east of Lake Oahe, but will continue west of the highway because he believes the U.S. Army Corps of Engineers lacks jurisdiction on private land. It wasn’t immediately clear how long of a stretch on which work will stop.

He also said he’ll rule on the Standing Rock Sioux Tribe’s challenge of federal regulators’ decision to grant permits to the Texas-based operators of Dakota Access pipeline, which will cross North Dakota, South Dakota, Iowa and Illinois, by the end of Friday.

A weekend confrontation between protesters and construction workers near Lake Oahe prompted the tribe to ask Sunday for a temporary stop of construction. Four private security guards and two guard dogs received medical treatment, officials said, while a tribal spokesman noted that six people – including a child – were bitten by the dogs and at least 30 people were pepper-sprayed.

Dakota Access attorney Bill Leone said during Tuesday’s hearing that if it weren’t for the stoppages, the section in question would be finished by the end of this week.