COLUMBIANA COUNTY ROAD PROJECTS
UPCOMING Projects
1. State Route 344, Leetonia
Estimated total cost: $2,366,000
Start date: Aug. 20, 2012; Estimated completion date: Aug. 15, 2013
The bridge deck of 344 east of Leetonia at the state Route 11 interchange will be replaced.
2. U.S. Route 62, SALEM
Estimated total cost: $332,682
Begin date: Dec. 11, 2012; Estimated completion date: May 1, 2013
Signal maintenance and repair will be done at the intersection of 62 and state Route 45, as well as 62 and state Route 14.
3. State Route 39, salineville
Estimated total cost: $1,282,110
Estimated begin date: Aug. 15, 2013; Estimated completion date: May 30, 2014
Slide repair will be done just east of Salineville.
4. U.S. Route 30, lisbon
Estimated total cost: $430,115
Estimated begin date: July 1, 2013; Estimated completion date: Oct. 31, 2013
Slide repair will be done about a half-mile east of state Route 172 near Lisbon.
5. U.S. Route 30 and State Route 39, east liverpool
Estimated total cost: $545,250
Estimated begin date: May 13, 2013; Estimated completion date: Oct. 31, 2013
Sign upgrades will be conducted on the U.S. route through East Liverpool and to the state route at East Liverpool.
6. State Route 154, negley
Estimated total cost: $248,130
Begin date: March 18, 2013; Estimated completion date: July 31, 2013
Bridge repairs will be done north of state Route 170 at Negley.
7. State Route 164, lisbon
Estimated total cost: $1,207,201
Begin date: April 1, 2013; Estimated completion date: Sept. 15, 2013
The bridge just south of U.S. Route 30 at Lisbon will be repaired.
8. State Route 7, columbiana
Estimated total cost: $3,671,967
Begin date: April 15, 2013; Estimated completion date: Aug. 30, 2013
The four lane route will be resurfaced from state Route 267 to just south of State route 14 near Columbiana.
9. State Route 39, wellsville
Estimated total cost: $1.586,910
Estimated begin date: May 1, 2013; Estimated completion date: July 31, 2013
The two lane route will be resurfaced from County Road 418 (Steubenville Pike Road) at Highlandtown to state Route 7 at Wellsville.
10. State Route 154, rogers
Estimated total cost: $2,289,914
Estimated start date: May 1, 2013; Estimated completion date: Oct. 31, 2013
The two-lane route will be resurfaced from Rogers to the Pennsylvania state line.
11. U.S. Route 30, east liverpool
Estimated total cost: $1,248,996
Estimated start date: June 1, 2013; Estimated completion date: Oct. 31, 2013
The bridge will be repaired about one mile east of state Route 39 at East Liverpool.
12. State Route 14, washingtonville
Estimated total cost: $1,181,287
Estimated start date: June 1, 2013; Estimated completion date: May 31, 2014
Intersection improvement will be made at the intersection of Washingtonville Road and East State Street in Washingtonville.
13. State Route 558, fairfield
Estimated total cost: $474,483
Estimated start date: June 1, 2013; Estimated completion date: Dec. 1, 2013
Culverts will be replaced about one mile east of state Route 11 between Franklin Square and East Fairfield.
14. State Route 7, LISBON
Estimated total cost: $884,611
Estimated start date: June 24, 2013; Estimated completion date: June 30, 2014
Highway lighting will be upgraded at the interchange of Clark Avenue, state Route 39 and state Route 45.
15. State Route 644, kensington
Estimated total cost: $299,108
Estimated start date: July 15, 2013; Estimated completion date: Oct. 31, 2013
Culverts will be replaced east of Kensington.
16. State Routes 518 and 644, summitville
Estimated total cost: $4,278,485
Estimated start date: Aug. 1, 2013; Estimated completion date: Oct. 31, 2013
Resurfacing will be done on 518 from County Road 413 to state route 45 at West Point, and on 644 from Kensington to Summitville.
43