Youngstown State University’s Board of Trustees is looking to take advantage of dropping interest rates and may borrow more money than originally planned to finance a variety of campus improvements. The original intent was to borrow $40 million with amounts designated, by priority, as follows:

Williamson College of Business Administration: $20 million

Land acquisition: $1 million

M2 parking deck demolition replaced with surface parking: $4.1 million

Tod Hall entrance: $450,000

Wick Pollock Inn: $3.95 million

Kilcawley House/Kilcawley Hall renovation: $10 million

STEM (Science, Technology, Engineering and Math): $500,000

POSSIBLE ADDITIONS

Williamson Hall conversion for classrooms etc.: $5.67 million

Jones Hall fourth-floor renovation: $1.3 million

Harrison Field relocation: $1.15 million

Greenway enhancements: $1 million