A schedule of area road construction projects:
MAHONING COUNTY
Lake Milton: Rehabilitation work continues on the Interstate 76 bridges over Lake Milton, with two-way traffic on the westbound side until mid-November. The $12.85-million rehabilitation project will last until mid-November 2003.
Youngstown: Interstate 680 is reduced to one lane in each direction from 7 p.m. to 7 a.m. and 9 a.m. to 2 p.m. to allow painting of seven bridges. Restrictions start at Four Mile Run Road in Austintown and continue to the Steel Street bridge. Completion date: end of October.
Austintown: The southbound lane of state Route 11 over Interstate 80-680 is closed for reconstruction of three bridges. A detour is provided. Completion date: Summer 2002.
Youngstown: The north state Route 11 off-ramp to west Interstate 80 is closed for a $4.1 million rehabilitation of lighting and three bridges. A detour is provided. Completion date: October 2002.
TRUMBULL COUNTY
Girard: State Route 11 north off-ramp to I-80 west is closed through Oct. 9 for reconstruction. The detour will follow state Route 11/I-80 northbound to Salt Springs Road to state Route 11/I-80 south to I-80 west.
Hubbard Township: The right-hand lanes of I-80 are closed from west of U.S. Route 62 to two miles east of Route 62 to repair and resurface pavement, paint 12 bridges and resurface seven bridges. Completion date: June 2002.
Hubbard Township: The Route 62 southbound bridge is reduced to one lane in each direction for bridge replacements over Little Yankee Creek. Completion date: Oct. 31.
Vienna, Fowler and Howland townships: Northbound lane of state Route 11 near King Graves Road is closed for ramp construction. King Graves over Route 11 is closed for bridge replacement work. Detour provided. Completion date: November.
Champion Township: State Route 5 east of state Route 45 will maintain one lane of traffic in each direction. Project is rehabilitation of two bridges on Route 5. Completion date: October or early November.