Power outages hit downtown

Friday, June 25, 2010

Staff report

YOUNGSTOWN

Power outages were experienced in the downtown area Thursday evening as some 60 Ohio Edison employees worked to repair underground cables to prevent a potential widespread outage.

The first planned outage began at 5 p.m., affecting the city garage’s traffic engineering and paint shop and some businesses, said David Turner, area manager for Ohio Edison. A second outage, initiated at 9 p.m., affected 20 Federal Place, Turning Technologies, the Rosetta Stone Cafe and a few more businesses, as well as the Mahoning County jail, which operated on a backup generator, Turner said.

All power was expected to be returned by 11 p.m. at the latest. However power was reportedly off for only a few minutes after 9 p.m.

“Our biggest concern was to get repairs done because as temperatures rise, and the demand increases, without repairs there is a good chance we’d have a major outage in the downtown area of greater duration and affecting more people,” Turner said.