FIGURES



FIGURES
Building costs
Judge Michael Bernard says the Girard Justice Center cost $4.5 million. City Auditor Sam Zirafi put the cost at $5.2 million. Judge Bernard's figures are:
Construction: $4,065, 253.
General contractor, $2,239,389. Electrical system, $608,578. Security system, $324,012. Heating and cooling, $595,387. Plumbing, $297,878.Land acquisition: $71,947. Real estate purchase, $65,000. Demolition of existing house, $3,400.
Soil core samples, $3,475 County filing fees, $72.Architectural and design: $322,164. Architect, $296,244. Security consultant, $25,920.Miscellaneous: $54,320. State permits, $5,219. Historical plaque, $658. Phone cable supplies, $5,147. Cable installation, $517. Phone system, $42,778.Total: $4,513, 685.
Source: Judge Michael Bernard